Work - Rhônexpress

Work is planned to extend tramway line T6 and create the future tramway line T9, requiring a temporary interruption of the Rhônexpress line.

Calendrier RX

March 12, March 17 to 19, March 24, 26 and 27, March 31 to April 3, April 7 and 8 :

- Until approx. 8.30pm : The Rhônexpress line runs from Vaulx-en-Velin La Soie to Lyon Saint-Exupéry AirportSolution

- From approx. 8.30pm : Rhônexpress line no longer runs => Relay buses will be provided between Vaux-en-Velin La Soie and the Airport

Solution total

February 25 to March 2, March 6 to March 9, March 13 to March 16, March 20 to March 23, March 25, March 28 to March 30, April 4 to April 6, April 9 to April 18 :

- The Rhônexpress line runs from Vaulx-en-Velin La Soie to Airport Lyon Saint-Exupéry

Solution

From April 19 to May 9 :

- The Rhônexpress line does not run => Relay buses will be provided between Vaux-en-Velin La Soie and the Airport
Solution total