Work - Line T3

Work is planned to extend tramway line T6 and create the future tramway line T9, necessitating the temporary interruption of line T7.T3 Calendar

March 3 to 5, March 10 to 12, March 17 to 19, March 24, 26 and 27, March 31 to April 3, April 7 and 8 :

 

  • Until approx. 8.30pm : Line T3 runs from Vaulx-en-Velin la Soie to Meyzieu Les Panettes (Meyzieu Zi at weekends
  • From approx. 8.30pm :T3 line no longer runs => Relay buses will be provided, and metro line A will be reinforced.

February 25 to March 2, March 6 to 9, March 13 to 16, March 20 to 23, March 25, March 28 to 30, April 4 to 6, April 9 to 18 : 

 

  • Line T3 runs from Vaulx-en-Velin la Soie to Meyzieu Les Panettes (Meyzieu Zi at weekends). => Relay buses will be set up, and metro line A will be reinforced.

From April 19 to May 9 :

 

  • Line T3 does not run => Relay buses will be provided and metro line A will be reinforced.